1998: Spring Valley, Enniscorthy

Description

The link-road at Spring Valley connects the new bridge in Enniscorthy to Shannon Hill. It twists around a steep incline giving a majestic view of the town and the surrounding countryside. Enniscorthy Town Council appointed Niall Barry & Co to carry out the civil engineering works. This included excavation, leveling, kerbing, drainage, footpaths and public lighting. Bennett Tarmacadam was responsible for the main surfacing which required final grade preparation, 60mm of 20mm dense base course macadam, 40mm of 30% 14mm hot-rolled asphalt wearing course and 20mm pre-coated chippings. The project was completed in January 1998. Please note that the above photos were taken in November 2003, approximately five years after the original work.

Client

Enniscorthy Town Council
Market Square
Enniscorthy
Co. Wexford

Tel  (054) 33540
Fax (054) 35115


While every care has been taken in compiling this information, it is supplied "as is" with no implied warranties.